Road Construction
Southern Palm Beach County Projects:
Atlantic Avenue / S.R. 806, from Via Flora to McNab Avenue
This $3.6 million, 2.7 mile construction project began on December 1, 2008, between Via Flora and McNab Avenue in Delray Beach. The work to be performed during this project includes: milling and resurfacing the roadway; replacing sidewalk curb ramps to meet current Americans with Disabilities Act (ADA) standards; and signalization, widening, and storm water drainage improvements at the intersection of Atlantic Avenue and Congress Avenue. The project is being built by Weekley Asphalt Paving, Inc. and is expected to be complete in fall 2009.
Restrictions: Daytime lane closures will occur, 7 a.m. until 3:30 p.m., Monday through Friday, at various locations within project limits. Motorists might encounter delays during these hours. One lane will remain open in each direction at all times.
Atlantic Avenue / S.R. 806, from NW/SW 12th Avenue to A1A
This $4.2 million construction project began January 5, 2009, from just east of I-95 to just west of A1A in Delray Beach. The work to be performed during this project includes: milling and resurfacing the roadway; replacing sidewalk curb ramps to meet current Americans with Disabilities Act (ADA) standards; and signalization, widening, and landscaping. The project is being built by Weekley Asphalt Paving, Inc. and is expected to be complete in late 2009.
Restrictions: Daytime lane closures will occur, 7 a.m. until 7 p.m., Monday through Friday, between SW/NW12th Avenue and Swinton Avenue and from Federal Highway to A1A, for project-related work. One lane will remain open in each direction at all times. However, on-street parking and access to side streets might be temporarily restricted. Detours will be established when necessary. Access to local businesses will be maintained at all times. Motorists might experience delays.
S.R. 7 / U.S. 441 from the Broward County Line to Glades Road
Construction on this 2.9 mile project began February 9, 2009. Work consists of milling and resurfacing, curb ramp replacement, guardrail, and signalization. The project will cost an estimated $4.7 million and is expected to last until late 2009. Work is being performed by Hardrives of Delray, Inc.
Restrictions: North and southbound single lane closures will occur between 9 a.m. and 4 p.m., at various locations between Glades Road and the Broward County Line, Monday through Saturday, for minor widening and other project-related work. At least two lanes will remain open in each direction at all times. Motorists should anticipate delays traveling through the area.
Powerline Road / S.R. 845 from the Broward County Line to Glades Road
Construction on this 3 mile project began Tuesday, May 26, 2009. Work consists of milling and resurfacing, minor widening and reconstruction, signalization, lighting, drainage, bridge replacement, irrigation and landscaping. The project will cost an estimated $9.7 million and is expected to last until summer 2011. Work is being performed by Ranger Construction Industries.
Restrictions: Travel lanes will be closed at various locations between Glades Road and the Broward County Line, 9 a.m. until 4 p.m., Monday through Friday, for project-related work. The contractor has installed temporary barrier wall and established continuous lane closures at various locations for drainage work in the median area. At least one lane will remain open at all times. Motorists should anticipate delays.